Pakistan Case Law← Search
K.L.R. 2001 Civil Cases 193

M/S. SUBHAN DEEPWELL CORPORATION vs PROJECT DIRECTOR, PUNJAB RURAL

CitationK.L.R. 2001 Civil Cases 193
CourtLahore High Court
Case No.Writ Petition No. 5473 of 2000
Date2000-12-01
Judge(s)Nazir Ahmed Siddiqui
ResultN/A

ORDER

NAZIR AHMAD SIDDIQUR J. ~ The following two writ petitions arising out of the common questions of law and facts, are being disposed of through this single judgment.

(1) W.P. No. 5458/2000 (M/s. Mufti Salu & Company Vs. Government of Punjab, etc.).

(2) W.P. No. 5473/2000 (M/s. Suhhan Deepwell Corporation Vs. Project Director).

2. Executive Engineer Punjab Rural Water Supply and Sanitation Project(s) Division I, II, Bahawalpur invited sealed percentage/item rate tenders (termed as short tender notice) from registered, renewed contractors/firms of Housing & Development and Physical Health Engineering Department for the year 2000-2001, who have been prequalified by Punjab Rural Water Supply and Sanitation Project Directorate, Lahore for its sub Projects as per Clause 4(a) Schedule III of Project agreement signed between the Asian Development Bank and Government of Pakistan and are eligible tor participation in tenders.

3. The petitioners in both the above mentioned writ petitions claimed to be approved Government Contractors in Category 'A'. They intended to participate in the above tenders but respondent No. 3 did not allow them, hence they filed the instant petitions with the following prayers:-

(i) Declaration may kindly be granted to the effect that the clog of pre-qualification upon the petitioner firm for tendering to be issued upto 25.11.2000 from the office of the respondent No. 3 and its receipts on 27.11.2000 is contrary to law, arbitrary, mala fide, without jurisdiction, without lawful authority and of no legal effect.

(ii) Direction may kindly be issued to the respondent to issue tenders to the petitioner's firm as per schedule of the "SHORT NOTICE" (Annexure-D).

(iii) An ad-interim be graciously granted in favour of the petitioner by suspending the operation of the Short Tender Notice.

(iv) Any other relief which this Hon'ble High Court deem fit and proper may graciously be awarded with costs in favour of the petitioner firm against the respondents in the larger interest of justice.

4. The learned counsel for the petitioners contends that petitioner being Class 'A' approved contractors are fully eligible to apply for tender in question particularly when their application for pre-qualification have already been entertained by the Project Director Punjab Rural Water Supply & Sanitation Project HUD & PHE Department and they were duly recommended by the competent Committee. Thus, the petitioners are being prevented from participating in the tender in question on the pretext of prequalification. Such an act on behalf of the respondents cannot be justified on any score either of law or justice.

5. On the Other hand learned AAG submits that the Projects for which tenders have been invited, are being financed by Asian Development Bank. As per clause-4(a) of the agreement executed between the Asian Development Bank and Government of Pakistan, those contractors are eligible to participate in the tenders whose pre-qualification has been approved by the Bank. The petitioners did apply for pre-qualification but so far no requisite approval by the ADB has been received, therefore, tenders cannot be issued to them.

6. I have given due consideration to the arguments of the learned counsel for the parties and perused the record. Admittedly 72% of the cost of the Projects in question is being financed by Asian Development Bank and in this context, an agreement was executed between the Bank and Government of Pakistan, a copy of which is annexed with the comments of the respondents. It is also an admitted position that applications were invited for grant of pre-qualification of firms and the petitioners in response thereto did submit their applications, which were duly entertained and processed by the Project Director and as per petitioners, they have also been recommended by a competent Committee but at the same time it could not be denied that the requisite formal approval in the context of prequalification of firms from the ADB has not been received. Since the condition precedent to participate in the coming tenders is that of prequalification approved by the ADB and the same has not yet been received, therefore, the petitioners cannot lawfully maintain or claim a right in respect of participation in the tenders, subject matter of these writ petitions. Since the terms and conditions of agreement are binding, therefore, no departure therefrom is permissible, particularly with reference to approval of pre-qualification by ADB.

7. Viewed from this angle respondents are helpless to adopt a course in order to accommodate the petitioners which could not have the sanction under the law and justice. Resultantly the act of respondents for not allowing the petitioners to participate in the coming tenders cannot be declared unlawful.

8. For what has been stated above, instant petitions fail and the same are dismissed.

For educational and research use only — not legal advice. Verify against the official report before relying on it. See our Disclaimer.
Disclaimer·Privacy·Terms·Search