Pakistan Case Lawโ† Search
2021 CLC 915

Executive Engineer, Highways Division Moro and 4 others vs Nazeer Ahmed

Citation2021 CLC 915
CourtSindh High Court
Judge(s)Adnan Iqbal Chaudhry
ResultRevision allowed

ADNAN IQBAL CHAUDHR Y J.----F.C. Suit No. 54/1993 filed by the Respondents / their predecessors (Plaintif fs) for compensation of land consumed in certain road construction projects, was dismissed by the learned Senior Civil Judge, Moro; however , in Civil Appeal No. 10/1999, the learned Additional District Judge, Moro, decreed the suit in part; hence this revision application by the Applicants (Defendants).

2. It was the case of the Plaintif fs that in 1972-73, the Government of Sindh constructed a road from Moro to Mithani (the 'first road project ') which utilized part of the Plaintif fs' ancestral land in Survey No. 373 of Deh Manaheen, Taluka Moro;' that in 1977-78,2 the Government constructed a road to village Puran (the 'second road project'), which utilized part of the Plaintif fs' land in Survey Nos. 349, 350 and 351 of Deh Manaheen; that again in 1993,2 the Government utilized the Plaintif fs' land in Survey Nos. 383, 385 and 782 of Deh Manaheen to construct the Nather Ditta Road' (the 'third road project'). It was contended that time and again the Plaintif fs approached the Executive Engineer Highways, Moro, for compensation of said land, but in vain; hence the prayer for damages @ Rs.100,000/- per acre.

3. Officers of the Highways Division were arrayed as Defendants 1 to 3. The Land Acquisition Officer was arrayed as Defendant No. 4. The Province of Sindh was arrayed as Defendant No. 5 althou gh it was wrongly sued through the Deputy Commissioner Naushahro Feroze. A written statement was filed by the Executive Engineer , Highways Division, Moro. The suit proceeded ex-parte against the Land Acquisition Of ficer and the Province.

4. It was the case of the Highways Division that while the said three road projects had been undertaken by them, the land for the same had been duly acquired by the Government under the Land Acquisition Act, 1894; that for acquiring the land for the first and seco nd road projects in the years 1972-73 and 1977-78 respectively , the Highways Division had made the prescribed payment to the Acquisition Office B&R, Hyderabad, who in turn had released compensation to the af fected {{FOOTNOTE}} 1 Plaint and deposition of PW -1, Nazeer Ahmed 2 Cross-examination of PW -1.

3 Cross-examination of PW -1.

4 Deposition of PW -1. {{FOOTNOTE}} khatedars, albeit in view of a higher rate subsequently recommended by the Deputy Commissioner Nawabshah, the matter with regards to additional compensation was still pending; that the Plaintif fs had never approached the Land Acquisition Officer for compensation; and that the third road project was constructed under a Senator Scheme sponsored under the Tameer-e-W atan Program. It was further contended that Survey No. 373 in Deh Manaheen claimed by the Plaintif fs, had never been utilized in the road projects.

5. By judgment and decree dated 12-1101998, the trial court dismissed the suit holding that the Plaintif fs had failed to prove that in the years 1972-73 and 1977-78 they were owners of the Survey Numbers claimed by them; that village Form-XV produced by the Plaintif fs was not reliable evidence of ownership of the land in question as the same was issued in the year 1980; and that in any case, the remedy of the Plaintif fs for compensation was before the authority/forum designated under the Land Acquisition Act, 1894.

6. On the appeal of the Plaintif fs (Respondents herein), the appellate court passed judgment for the Plaintif fs holding that village Form-XV was sufficient evidence of the Plaintif fs' ownership of Survey Nos. 349, 350 and 351; that the evidence showed that land in Survey Nos. 349, 350 and 351 had been acquired by the Government for constructing a road to village Puran (second road project) for which the Plaintif fs were not compensated; and by a preliminary decree dated 19-05-1999, the appellate court proceeded to appoint a commissioner to determine the rate of land and the area acquired. On receipt of the commissioner's report, the appellate court then passed a final decree dated 23-10-1999 awarding compensation to the Plaintif fs @ Rs.100,000/- per acre to the extent of 4-07 acres of land in Survey Nos.349, 350 and 351 of Deh Manaheen, Taluka Moro, i.e. a sum of Rs.417,500/-.

7. Thus, while the trial court held that the Plaintif fs had not been able to prove ownership of any part of the land claimed in the suit, the appellate court held that the Plaintif fs had been able to prove ownership of least of Survey Nos. 349, 350 and 351, The Plaintif fs did not appeal the denial of relief for the other Survey Numbers. Therefore, it is only Survey Nos. 349, 350 and 351 of Deh Manaheen that are relevant to this revision.

8. The learned A.A.G. Sindh submitted that suit for compensation for land acquired in 1972-73 and 1977-78 was time-barred; that the appellate court mis-read the evidence in holding that the Plaintif fs had proved ownership to the land in question; and that, since the land had been acquired under the Land Acquisition Act, 1894, and since the Plaintif fs had not approached the authority/forum under the said Act for compensation, the civil court could not have exercised general jurisdiction to decide the question of compensation as so held in Abdul Manan v. Chairman WAPDA (1990 CLC 1377).

9. Heard the learned AAG Sindh and perused the record.

10. In their objections to this revision, the Respondents (Plaintif fs) have taken the plea that the revision is time- barred. I advert to that objection first.

The preliminary decree passed by the appellate court is dated 19-05-1999. The final decree is dated 23-10-1999.

The revision is directed against both. From the final decree, this revision application filed on 20-01-2000, on the 89th day, is within the limitation of 90 days. However , if separate limitation is comp uted for the preliminary decree, then to that extent the revision is delayed by 156 days. But then, section 97, C.P.C. which precludes a party from disputing the correctness of a preliminary decree in an appeal from the final decree when no appeal was preferred from the preliminary decree, does not put the same restriction on a revision application. Rather , under section 115, C.P.C., a revision is against a 'case decided'. However , that is not to say that a revision application can never be filed against a preliminary decree before the passing of a final decree, inasmuch as the terms of a preliminary decree may well be a 'case decided' within the meaning of section 115, C.P.C.5 Nevertheless, in my view, where the question is to the very jurisdiction of the sub-ordinate court to decide the case, such question remains open in a revision from the final decree even though no revision application had been preferred from the preliminary decree.6 Thus, this revision is within limitation.

11. I now advert to the grounds of the revision. It appears that to hold that the Plaintif fs had proved ownership to Survey Nos. 349, 350 and 352 of Deh Manaheen, the learned appellate court relied on village Form-XV produced by the Plaintif fs. Suf fice to observe that in the {{FOOTNOTE}} 5 For what is 'case decided' within the meaning of section 115, C.P.C., see Anjum Chemical Storage (Pvt.) Ltd. v.

Chenab Ltd. Nishatabad (2016 SCMR 177), and Nestle Milkpak Ltd. v. Classic Needs Pakistan (Pvt.) Ltd. (2006 SCMR 21 )

6. In Hafeez Ahmed v. Civil Judge, Lahore (PLD 2012 SC 400), the Supreme Court held that if the High Court or the District or the District Court, as the case maybe, is of the view that the case decided by the sub-ordinate suffers from a jurisdictional error and must be corrected, the fact that the revision application is beyond the prescribed time is no impediment, as the Court can nonet heless exercise suo motu powers under section 115, C.P.C. to correct the error. {{FOOTNOTE}} absence of any document / entry to show title of the Plaintif fs' predecessors through whom the Plaintif fs claimed to have inherited Survey Nos. 349, 350 and 352, village Form-XV on its own was hardly proof of ownership to the said land.

12. Be that as it may, like the trial court the appellate court too found that the land claimed by the Plaintif fs in Survey Nos. 349, 350 and 351 had in fact been acquired by the Government unde r the Land Acquisition Act, 1894 for the public purpose of constructing a road. The learned AAG Sindh has also filed a copy of notice dated 27-12- 1994 issued under section 9 of the Land Acquisition Act, and the award dated 18-05-1995 made under section 11 thereof in respect of land acquired for constructing the road to village Puran, Taluka Moro, which included the subject Survey Nos. 349, 350 and 351. From the award it appears that while the said land was occupied by the Government in the year 1986, the notice inviting claims for compensation pursuant to section 9 of the Land Acquisition Act was delayed until 1994, after the suit had been filed in 1993. However , even after the suit, when compensation proceedings under the Land Acquisition Act were disclosed in the written statement of the Highways Division, the Plaintif fs did not file a claim for compensation before the Collector pursuant to section 9 of the Land Acquisition Act, nor did they move under section 18 thereof for making a Referenc e against the award to the court designated for such purpose. The acqu isition proceedings remained unchallenged. Therefore, the suit of the Plaintif fs cannot be said to be one envisaged under section 52 of the Land Acquisition Act to question anything done in pursuance of the said Act.

13. In the circumstances of the case, given the failure of the Plaintif fs to invok e the special jurisdiction of the designated court under section 18 of the Land Acquisition Act, 1894, there was an implied bar, as contemplated under section 9, C.P.C., to the general / plenary jurisdiction of the civil court to decide the Plaintif fs' suit for compensation. Such implied bar could only be circumvented if the Plaintif fs demonstrated that the case attracted one of the established exceptions to the ouster of the plenary jurisdiction of a civil court,' which, as already noted, was not the case set-up by the Plaintif fs.

14. For the foregoing reasons, the decree passed by the appellate court awarding compensation for land acquired under the Land Acquisition Act, 1894, was without jurisdiction. Accordingly , this revision application is allowed; the judgment, the preliminary decree and the final decree passed by the appellate court in Civil {{FOOTNOTE}} 7 (sic) {{FOOTNOTE}} Appeal No. 10/1999 are set-aside; and the judgment and decree passed ID by the trial court dismissing F.C. Suit No. 54/1993 is restored.

For educational and research use only โ€” not legal advice. Verify against the official report before relying on it. See our Disclaimer.
DisclaimerยทPrivacyยทTermsยทSearch